seci-invites-bids-for-125-mw-500-mwh-standalone-bess-projects-in-odisha
PROJECT OVERVIEW
Setting up of 125MW/500MWH standalone Battery Energy Storage System in Odisha under Tarrif Based Competitive Bidding with Viability Gap Funding supported through PSDF.
TYPE OF TENDER
Single stage Two Envelope Online Bidding system followed bye-reverse Auction
KEY DATES
Tender Release Date - 18/12/2025
Pre-Bid Date - 2/01/2026https://wwseci-invites-bids-for-125-mw-500-mwh-standalone-bess-projects-in-odisha
Bid Submission Date - 20/02026
Reverse Auction - yes
Bid Validity - 12 months
Maximum Capacity - 125MW
Minimum Capacity - 125MW
Project - 125MW/500MWH Standalone BESS(4 hr storage)
Location - Setup inside the identified Substation of the STU network in the state of odisha.Land will be provided on Right to use basis to the BESS.
Procurer/End Buyer - Gridco/Optcl
VGF - INR1800000 per MWH
BESPA Period - 15 Years Supply to Gridco
EMD - INR900000 per MW
PBG - INR2250000 Per MW
BID Processing Fees - Max INR1500000+GST
ELIGIBLE CRITERIA
Technical Eligibility
Proposed to promote only commercially
Financial Eligibility
Net worth - INR9000000/MW
Minimum Annual Turnover - INR5292000/MW
PBDIT - INR1058409/MW
LC- INR1323000/MW
Financial Bid Evaluation - INR/MW/month
SCD (Commissioning schedule & LD)
18 months from the effective date of BESPA,With Applicable LD,shall be limited to the date as on 6 months from the SCD or the extended SCD.The Total amount for the project shall be encashed on per day basis.
Land
Land identification,lease Right to use is under GRIDCO.Developer must access site condition,no later claim accepted.
Connectivity
Voltage for interconnection at the STU grid shall be 33 Kv
Financial Closure
6 months from the date of Singing of the BESPA
RTE - 85%
Billing & Payment Terms
GRIDCO shall pay to the BESSED the monthly Tarriff Payment
Amount Claimed by GRIDCO,if any from the BESSED will be adjusted from the monthly energy payment.In case of any excess payment adjustment 1.25% Surcharge will be applicable on day to day basis
Late Payment Surcharge
Delay in payment of a Monthly Bill by GRIDCO,the late payment Surcharge shall be claimed by the BESSED through the supplementary Bill.
Rebate
1.5% shall be payable to the GRIDCO with in 10 days
Any payment after 10 days upto the 30th day shall be 1%
Beyond 35 days no rebate
Scope
Supply of All equipment & material
The developer must supply:
Battery racks, container
Pcs, Transformer, switchgear, protection panel
Fire protection & safety system
HVAC & auxiliary system
SCADA, communication system
All cables and earthing system
Testing & commissioning
The Scope includes:
Pre commissioning test
Performance testing as per BESPA
Demonstration of guarantee parameters:
Power
Energy
RTE
Response time
Availability
Compliance, certificate & clearances
Comments
Post a Comment